How long does commercial AC installation actually take?

Real UK timelines by scope — survey, design, install and commissioning — plus the four things that always cause delay, and how to run them in parallel.

install-timeline
In short

A typical 4-zone office AC install runs 4–6 working days on site after a 1-week design and 3–6-week landlord L4A — end-to-end 6–10 weeks. Single splits take a day. Whole-building VRF takes 3–6 weeks on site.

Timeline by scope

Working days on site, and the phases around them.

ScopeSurveyDesignInstallCommission
Single wall-mount split (one room)1 day2–3 days1 daySame day
4-way cassette, single office1 day3–5 days1–2 days0.5 day
Multi-split, 4 zones (200 m² floor)1 day1 week4–6 days1 day
VRF, single floor (250 m²)1–2 days1–2 weeks7–10 days1–2 days
VRF, whole building (1,000 m²+)2–3 days3–4 weeks3–6 weeks3–5 days
Server room CRAC (with N+1)1 day1–2 weeks3–5 days1 day
The four delay causes

The things that push a 6-week job to 12.

  • Landlord Licence for Alterations

    L4A negotiation is the single biggest hidden delay — 3–6 weeks is typical, longer if the landlord's surveyor requests a structural sign-off. Start it the day the design is signed off, not after.

  • Long-lead equipment

    Standard Daikin cassettes and splits: 2–3 weeks. Higher-capacity VRV condensers and specialist CRAC units: 6–10 weeks. Confirm lead time at quote — not at PO.

  • Planning consent for condensers

    Rooftop condensers in a conservation area or on a listed building need planning — 8 weeks minimum. Ground-floor condensers rarely do. AccuTemp flags this in the initial site survey.

  • Building access windows

    Out-of-hours installs on live floors are efficient but sensitive to shared risers, security escort availability and neighbour restrictions. Confirm access windows before locking a start date.

Related: office installation process, cost guide, VRF vs split, sizing guide, emergency response.

Frequently asked questions

How long does commercial AC installation take?
For a typical UK commercial office, the installation itself takes 4–6 working days for a 4-zone system covering a 200 m² floor. Add 1 week for survey and design, and 3–6 weeks for landlord Licence for Alterations. End-to-end, from first contact to commissioning, a routine office fit-out lands at 6–10 weeks.
How long does a VRF system take to install?
A single-floor VRF (~250 m²) takes 7–10 working days on site. Whole-building VRF across 1,000 m² or more typically runs 3–6 weeks depending on riser access and simultaneous trades. Programmed weekend and out-of-hours work is standard.
What's the biggest cause of delay?
Landlord Licence for Alterations. It's a fixed 3–6 week negotiation and it can't be compressed. Second is condenser planning consent in conservation areas or on listed buildings — 8 weeks minimum. Start both in parallel with the design, not after.
Can commercial AC be installed while the office is in use?
Yes. We routinely install on live floors — brazing and refrigerant work happen out-of-hours, cassette drops and controls commissioning during standard hours. Occupants generally lose access only to the specific meeting room being worked on that day.
Need a firm date

Book a scoping call — we'll issue a Gantt with your quote.